Renaico II Wind Farm

One of the biggest projects of South America.

Due to the magnitude of the construction area (with an extension of approximately 68 hectares), the project required the installation of 3 site facilities with an area of 10 000 m2 each.

Also, due to a massive material requirement, a concrete batching plant had to be installed on site. All this for the construction of a 38 m bridge, 60 km of access roads, and 77 foundations involving large amounts of materials, such as 600 000 m3 of earthmoving, 650 000 m3 of aggregates for the construction of accesses, platforms, and backfill (with a daily average of 30 trucks), 7 500 000 kg of steel and 55 000 m3 of concrete for the construction of foundations and other minor works, such as Box Culverts, pavements, etc… More than 450 people were involved, daily, to make this project happen. CJR Renewables proudly fulfilled the goals and timeline.

Project details
Client Enel Green Power
Area Balance of Plant (BoP), Power & Grid (EPC)
Location Araucanía, Chile, Chile
Implementation time 586 days
Installed Power 134.4 MW
Wind Turbines 32 Goldwin GW155 4200kW
youtube
Parque Eólico de Renaico II 2
Parque Eólico de Renaico II 0
Parque Eólico de Renaico II 3
What have we done

// Balance of Plant (BoP)

23 km Access Roads

32 Platforms

32 Foundations

8 km Cable trenches

194 km Medium Voltage Cables

 

// Power & Grid (EPC)

// Expansion of Elevating Substation - 33/220 kV