One of the most important substations in Chile that allows the integration of several projects to the grid.

CJR Renewables performed the complete engineering, procurement and construction of this challenging project. This is one of the largest wind energy projects in Chile.

Project details
Client Pacific Hydro Chile
Area Balance of Plant (BoP), Power & Grid (EPC)
Location Coquimbo, Chile
Implementation time 520 days
Installed Power 80 MW
Power & Grid 33/220 kV Substation, Interconnection Substation
Wind Turbines 32 GOLDWING 2,5 MW
youtube
Punta Sierra Wind Farm 1
Punta Sierra Wind Farm 2
Punta Sierra Wind Farm 3
Punta Sierra Wind Farm 4
What have we done

// Earth Movements

// Access Roads

// 32 Foundations & Platforms

// 31.5 kV Internal Medium Voltage Network

// 33/220 kV Substation

// Interconnection Substation

// Overhead High Voltage Line (1 km)