CJR Renewables awarded Piiparinmaki Phase II

CJR Renewables awarded Piiparinmaki Phase II 0

The second phase figures the installation of 28 wind turbines V150 5.6 MW (Enventus), which came to add up 156.8 MW to the project when compared to the first phase, which involved 54,6 MW and 13 wind turbines. The project will have more than 35 people and two crane lines and must be fulfilled within a 23 weeks schedule. To João Jordão, this project has one significant advantage," CJR Renewables is installing Simo's project (151,2 MW), located about 300 km away. This small distance is an added value for both projects, advocating mutual help in adversities and challenges and cost-effectiveness". João also added that he is very proud of this award once "a second phase is only possible because of the excellence we embrace the first project." With this award, CJR Renewables totals 540.5 MW installed in Finland.