Tocha Wind Farm

This wind farm was constructed on the Portuguese coast, on a terrain mostly formed by sand. CJR Renewables had to comply with a tight schedule, high customer standards regarding Control & Protection System. The focus was heavily placed on supply chain management, guaranteeing that all key suppliers would be able to meet the project schedule, complying with the agreed grid connection date. The soil resistivity led to particular technical solutions, in order to reach resistance values above 1 ohm, in compliance with applicable standards.

Project details
Client EDP Renewables / Vestas
Area WTG Installation; Wind Farms Construction (BoP); Power & Grid
Location Figueira da Foz, Portugal
Implementation time 120 days
Installed Power 9 MW
Wind Turbines 5 Vestas V100 1,8 MW
Tocha Wind Farm 2
Tocha Wind Farm 1
Tocha Wind Farm 3
What have we done

// Foundations

// Hardstands

// 15kV Switchstation

// Internal Medium Voltage (MV) Network

// Connection to 15kV Line

// WTG Mechanical & Electrical Installation