Korytnica Wind Farm

The experienced CJR Renewables team was up to it and with a perfect time management, as well as efficient management of resources and suppliers, complied with the set schedule and finished the project with maximum quality.

Project details
Client WF Korytnica SP. Zoo
Area Wind Farms Construction (BoP)
Location Korytnica, Poland
Implementation time 275 days
Installed Power 82.5 MW
Wind Turbines Vestas V126 3,3 MW
Korytnica Wind Farm 0
Korytnica Wind Farm 1
Korytnica Wind Farm 2
Korytnica Wind Farm 4
What have we done

// Access Roads (27 km)

// Foundations & Platforms

// 42 km of cable trenches

// 200 km of cable laying