Budziechów Wind Farm

The biggest challenge was to comply with the Grid Connection schedule, once the design, that required final approval from authorities, came later than expected. This forced CJR Wind Team to work under record time in order to fulfil client's Grid Connection in time (so our client had no consequences in the agreed FIT).

Project details
Client Gewind
Area Wind Farms Construction (BoP)
Location Budziechów, Poland
Implementation time 106 days
Installed Power 6.4 MW
Wind Turbines Senvion 3.2M
Budziechów Wind Farm 2
Budziechów Wind Farm 0
Budziechów Wind Farm 3
What have we done

// Access roads

// Foundations & Platforms

// Cable trenches

// 19 km of Medium Voltage Cable Network

// 20kV Switchstation