The last foundation was poured today at 37.4 MW Wind Farm (Mlawa)

The last foundation was poured today at 37

Nuno Gonçalves, Project Manager, highlighted that "CJR Renewables started this wind farm construction last September and, due to weather contingencies, the works suffer some delays. But, despite this slip-up that has gotten out of our control, we are now making everything we can to recover time and allow the WTG installation teams to enter Mlawa Wind Farm on the scheduled date. I’m sure with the commitment all team has, we will make it happen”. Please recall that CJR Renewables is in charge of the complete BoP (civil works), including 17 foundations, 17 platforms, and 16 km of roads.