Burgos I & II Wind Farm

One of the largest renewable energy projects of the country.

Works were performed under very high temperatures (30°C and 45°C). A demanding project schedule, with the mechanical installation of 5 WTG per week and the delivery of 6 WTG per week, ready for commissioning. In order to be compliant with the schedule, the works were performed using 2 main cranes.

Project details
Client Sarens
Area WTG Installation
Location Burgos, Ilocos Norte, Philippines
Implementation time 146 days
Installed Power 150 MW
Wind Turbines 50 VESTAS V90 3.0 MW
Burgos I and II Wind Farm 0
Burgos I and II Wind Farm 0
Burgos I and II Wind Farm 2
Burgos I and II Wind Farm 4
Burgos I and II Wind Farm 5
What have we done

// WTG Mechanical & Electrical Installation