Project Details
Client
SARENS
Scope
WTGs Mechanical & Electrical Installation
Localization
Burgos, Ilocos Norte - Philippines
Implementation Time
146 Days
installed power
150 MW
Challenges //
Solutions
Works performed under very high temperatures (30°C and 45°C).

Demanding project schedule, with mechanical installation of 5 WTG's per week and delivery of 6 WTG's per week, ready for commissioning. In order to be compliant with the schedule, the works were performed using 2 Main Cranes.
Project
Characteristics
Wind Turbines
50 VESTAS V90 3.0MW
Hub Height
75 meters
Rotor Diameter
90 meters
What we did
BALANCE OF PLANT (BoP)
  • WTGs Mechanical & Electrical Instalation