Project Details
Client
GEO Renewables
Scope
Balance of Plant (BoP)
Localization
Dolnośląskie Voivodeship, District Zgorzelec - Poland
Implementation Time
270 Days
installed power
26 MW
Challenges //
Solutions
Part of the underground cables network was performed using the existing asphalted roads on Zgorzelec city.

The works were performed during winter time, with snowy days and frozen soil. In order to minimize damages on the asphalted roads, instead of opening traditional cable trenches, we've opted to execute drillings under the roads. A total of 1,2km of drilling works were performed, thus avoiding any damages on the existing roads.
Project
Characteristics
Wind Turbines
13 Vestas V100 2MW
Hub Height
105 meters
Rotor Diameter
90 meters
What we did

BALANCE OF PLANT (BoP) 

  • Construction of roads
  • Foundations
  • Hardstands
  • Electrical Substation
  • Internal Medium Voltage Network
  • 110kV UHVL with a length of 5 km
  • WTGs Mechanical & Electrical Installation
x