Project Details
Client
Mainstream
Scope
EPC
Localization
Atacama, Chile
Implementation Time
432 Days
installed power
170 MW
Challenges //
Solutions
Out of 196 towers, 140 required the use of a spectacular and faster means of transportation than traditional ones: the helicopter.
We had the collaboration of nearly 500 people in the project, divided into two major areas: civil engineering, with approximately 300 workers, and the installation works, with over 200 employees. Sometimes we used nine helicopters a day, which involved the transportation/operation of approximately 50 people on a daily basis.
Some employees also travelled in unsual means of transportation: on horseback, while others would walk for miles to reach some inhospitable locations.
Project
Characteristics
Wind Turbines
50 Senvion 3.4 M114
What we did

  • 43 km of access roads
  • 50 foundations and platforms
  • Hardstands
  • 281 km Medium Voltage Network
  • 400/115/33 kV Substation
  • 220 kV High Voltage Line (72 km)