Project Details
Client
ENLIGHT
Scope
BOP (BALANCE OF PLANT) WTG INSTALLATION
Localization
SERBIA
Implementation Time
300 Days
installed power
104 MW
Challenges //
Solutions
THE LARGEST WIND PROJECT IN SERBIA :Challenging and motivating are the words of this project, in which CJR Renewables has used innovative technology on the access roads to adapt materials to natural conditions of the territory.
Project
Characteristics
Wind Turbines
38 GE 2,75 MW
What we did

 

  • Earthing Systems
  • 38 Foundations & Platforms
  • 40 km Access Roads
  • Preliminary & Detailed Design - Civil / Electrical Infrastructure
  • 39 km Cable Trenches
  • SCADA & Protection Systems and Plant Monitoring
  • Substation 220 kV
  • 33/220kV Control Building & 220kV interconnection
  • Facilities: Switchyard and Control Building
  • 1.65 km Overhead High Voltage Line
  • Commissioning, Tests & Start-up
  • WTG Installation

 