Project Details
Client
GE
Scope
BOP
Localization
VOJVODINA, SERBIA
Implementation Time
361 Days
installed power
158 MW
Challenges //
Solutions
THE LARGEST WIND PROJECT IN SERBIA : During the construction phase, CJR Renewables was able to positively overcome every challenge, so that it even preceded the
deadlines of the project. Once in full production, the energy produced can displace more than 370.000 tons of carbon dioxide per year
Project
Characteristics
Wind Turbines
57 GE 2,78 MW
What we did

 

  • Preliminary & Detailed Design - Civil / Electrical Infrastructure
  • Earth Movements
  • 57 Foundations & Platforms
  • 58 km Access Roads
  • 56 km Cable Trenches
  • Earthing Systems

 