Project Details
Client
ENEL GREEN POWER
Scope
EPC
Localization
PERU
Implementation Time
323 Days
installed power
132 MW
Challenges //
Solutions
This project was quite ambitious and had a tight schedule. CJR Renewables was able to complete all challenges faced, such as adverse weather conditions due to desert location. As in all projects, CJR Renewables integrated local community and foster numerous QHSE practices. This was the first work of CJR Renewables in the country, that will contribute for the sustainable grow and environmental protection.
Project
Characteristics
Wind Turbines
42 ACCIONA 3.15 MW
What we did

 

  • Interconnection Substation 220 kV               
  • 42 Foundations & Platforms
  • Substation 33/220 kV & Control Building
  • MV Cable Trenches (171 km)
  • 58 km Access Roads
  • Earth Movements
  • Overhead High Voltage Line 220 kV

 