Project Details
Client
Senvion
Scope
WTG Installation
Localization
Buseto, Italy
Implementation Time
79 Days
installed power
22 MW
Challenges //
Solutions
In this project our team not only met with the schedule as well as finished all the work of installation earlier than planned.
Project
Characteristics
Wind Turbines
Senvion MM92
Hub Height
80 meters
Rotor Diameter
92 meters
What we did
WTG Mechanical & Electrical Installation