Projects
Wind Project
Moimenta I & II Wind Farm
Portugal
375Days
of implementation
84
MW
installed power
Project Details
Client
Âncora Wind & Senvion
Scope
Civil Works & WTG Installation
Localization
Portugal
Implementation Time
375 Days
installed power
84 MW
Challenges
//
Solutions
Due to environmental constraints the project had to be postponed on some occasions, but the team of CJR Renewables was able to meet with the planned schedule. This project, that counted with an artistic intervention of Joana Vasconcelos e Vhils in two WTGs, is a landmark project of CJR Renewables, that had made 33 km of access roads, 42 foundations and the installation of all WTG in a record time.
Project
Characteristics
Wind Turbines
Senvion MM 92
Hub Height
98-100 meters
Rotor Diameter
92,5 meters
What we did
Civil Works & WTG Installation
Construction of roads (33 km)
Foundations (42 foundations concreted in 6 months)
Hardstands
WTG installation (Electrical and Mechanical) of 42 WTG
Share this product:
Back
to projects
Next
x
Your browser is outdated, has security flaws and may present problems to view this and other websites.
Resolve Now
Our website uses cookies to help enhance your user experience. By using the Website, you confirm that you accept its use. We hope you agree.
Use of Cookie Policy.
Close
M&A DIGITAL
Newsletter