Project Details
Client
ISOTRON
Scope
PV PLANT SUBSTATION
Localization
Atacama, Chile
Implementation Time
95 Days
installed power
0 MW
Challenges //
Solutions
Located on a remote area of Atacama Desert, with adverse weather conditions, and with a tight planning to apply with, this project involved a lot of logistics challenges, which CJR was able to manage with a proper resources allocation.
Project
Characteristics
Substation
2 x 35 MW 220 / 23 kV
What we did

Civil Works - PV Plant Substation (Balance of System)

 

 

  • Substation & Control Building
  • Foundations & Platforms
  • Cable Trenches and ducts
  • Access Roads of substation 

 