Project Details
Client
Cândido José Rodrigues S.A.
Scope
Engineering, Procurement & Construction (EPC)
Localization
Lordelo, Guimarães - Portugal
Implementation Time
26 Days
installed power
0,09 MW
Challenges //
Solutions
Within a difficult schedule, and hard conditions to accesses and assembly the panels on the rooftop of the building, this project involved a careful study and analysis. The rehabilitation of the existing MV Switch Station was, also, an important part of the process.
Project
Characteristics
Switch Station
MV SwitchStation 15 / 0.4 kV | 400 kVA
Solar Panel
432 BYD 255 P6C - 30
What we did

Engineering, Procurement & Construction (EPC)

 

 

  • Aluminum Roof Structures
  • Installation of 432 PV Modules (255 Wp)
  • Electrical Inverter Installation
  • Earth Connections
  • Electrical Cables and Connectors Installation
  • Grid Connection
  • Maintenance

 