Project Details
Client
EDP Renewables Romania
Scope
Balance of Plant (BoP)
Localization
Facaeni, Ialomita - Romania
Implementation Time
209 Days
installed power
72 MW
Challenges //
Solutions
Although being one of the largest wind farms built in Romania, this project was implemented in record time despite the challenging weather conditions
Project
Characteristics
Wind Turbines
24 VESTAS V112 3.0 MW
Hub Height
119 meters
Rotor Diameter
112 meters
What we did
BALANCE OF PLANT (BoP)

  • Construction of roads
  • Piled foundations
  • Hardstands
  • 33kV Internal Medium Voltage Network
  • 400/115/33kV Substation
  • 400kV UHVL