This week we are starting Wielkopolska Wind Farm construction. For Luís Alves, Construction Manager, "our first focus will be earth movements in accesses roads and platforms. Despite being the week "zero" on the ground, incisive planning has been underway for more than two months now. It will seem that this construction will happen quite fast, if, of course, the weather conditions allow it".
This wind farm will have a total capacity of 26 MW and CJR Renewables is in charge of the complete BoP (civil and electrical works), including the 13 foundations, 13 platforms, 54 km of Medium Voltage Line (168 km of MV Cables), and 10 km of access roads.