Guleslettene Wind Farm

August 12, 2020 / CJR Renewables
From a total of 47 wind turbines, we already installed 37. “Our rhythm is quite high with the assemble of six turbines per week and 50 operational people making their best to accomplish an efficient execution in eight-hour shifts and two assembly lines. Last two weeks, unfortunately, we had a lot of breaks (driven by bad weather conditions), but our expectation is that luck is on our side, and next two weeks we intend to install the last 10 wind turbines.” Refers Paulo Amaro, WTG installation Supervisor.

Please recall that this project is "One of the biggest projects ever for the WTG Installation Business Unit (BU) and thus a landmark project for 2020", says António Vieira, Head of the BU.

Guleslettene Wind Farm, when energized, will count with 47 Wind Turbines V136 (90m HH), of 4 MW each, and a total output capacity of 188 MW.
August 12, 2020 / CJR Renewables
x
Our website uses cookies to help enhance your user experience. By using the Website, you confirm that you accept its use. We hope you agree. Use of Cookie Policy.
M&A DIGITAL Newsletter