PUNTA SIERRA WIND FARM: ENDING DAYS

August 6, 2018 / CJR Wind
CJR Renewables team, on 8th July, energized the Punta Sierra Wind Farm.

 

 

Another important step in Punta Sierra project was completed, with the conclusion of the sectioning works in circuit No. 2 of 220 kV line of the Central Interconnected System, which ended in the energization of the circuit No. 2 of Punta Sierra Substation.

For Luís Alves, Project Manager of this project, this stage was a " worthy achievement, since we are talking about a very complex substation with an area of 4 hectares. It was an beautiful journey . "


The next and last step will be to energize the entire MV network and the Unit Substations, which will allow the commissioning of all wind turbines.

August 6, 2018 / CJR Wind