CJR Renewables has secured a 60,90 MWp Solar Project order

October 1, 2019 / CJR Renewables
CJR Renewables pipeline just added another solar project, to be built in Chilean Atacama region.

 

CJR Renewables will perform all BoS works of this Solar Plant, including civil Works, such as earthworks, foundations, roads, MV and BT trenches & electrical works like PV modules (assembly), cables, SCADA, CCTV, tests and commissioning.

The ampliation of the existent substation of this PV plant will also receive Power & Grid teams with EPC works as the scope, which will include civil works such as earthworks, foundations, O&M building & electrical works such as HV equipments, MV switchgears, SPCC, auxiliary services, tests and commissioning.

With an projected timeline of 8 months in PV Plant construction and 4 months in Substation works, this Solar Project will count with 154 170 un of PV modules of 395 Wp, 13 PV Stations of 4MW and  1 713 Trackers – type 1P90 and once constructed, it will be the largest Solar PV Plant in CJR Renewables portfolio.  

The project and customer are undisclosed .


 

October 1, 2019 / CJR Renewables
x
Our website uses cookies to help enhance your user experience. By using the Website, you confirm that you accept its use. We hope you agree. Use of Cookie Policy.
M&A DIGITAL Newsletter