Punta Sierra WF: Civil works almost done

November 2, 2017 / CJR Wind
Having started in mid-January, CJR Renewables is near to complete the civil works (BoP) of Punta Sierra wind farm.
18 foundations are concreted, 90 percent of the work in earth moving, excavations and platforms are made and the 23 km of the access roads will be finished in within two weeks. 
Please recall that CJR Renewables was awarded with the EPC works for Punta Sierra Wind Farm - Chile (80 MW - 32 WTG's Goldwind 2.5MW).
This is a turn-key project that includes the development of all detailed engineering, execution of all civil and electrical works, supply and assembly of all associated facilities and equipment's:
- Earth movements;
- 32 WTG's foundations;
- Platforms;
- 23 km Access and roads;
- Cable trenches;
- Collector Networks: Medium Voltage, Earthing and Communications;
- WF Substation 220/31.5 kV Control Building and High Voltage Yard;
- Development and implementation of SPCC and Communications System with Local Utility.