Turnkey project on Jamaica

January 21, 2015 / CJR Wind
CJRWind was awarded and signed the Contract regarding the BoP works for Munro Wind Farm - Jamaica (36MW - 11 WTG's VESTAS V112 3.3MW).
This is a turn-key project (Civil and Electrical Works) that includes the development of all detailed engineering, execution of all civil works, supply and assembly of all associated facilities and equipments:
- WTG’s foundations;
- Cable trenches;
- Access and roads;
- Platforms;
- Command and Control Building and High Voltage Yard;
- Internal networks: medium voltage, earthing and communications;
- WF Substation 34.5 - 69 kV;
- Development and implementation of SPCC and Communications System with Local Utility.

With this project, CJRWind strengthens its presence in the renewable energy market in Jamaica, continuing a first project implemented in 2010: Wigton II (18MW - 9 WTG’s VESTAS V80 2MW).
 
With an expected schedule of eight months, this works will start in the middle of February. 

January 21, 2015 / CJR Wind
x
Our website uses cookies to help enhance your user experience. By using the Website, you confirm that you accept its use. We hope you agree. Use of Cookie Policy.
M&A DIGITAL Newsletter